The Board of Directors (the “Board” or “Directors”) of Wilton Resources Corporation Limited (the “Company”), and together with its subsidiaries, (the “Group”) wishes to provide an update on the Ciemas Gold Project. Infrastructure As at the date of this announcement, the following infrastructure has been completed: (i) land clearance for the mining area, processing plant area and hauling road; (ii) construction of the supporting infrastructure including laboratory, gold room, base camp, hauling road and stockpile area; and (iii) installation of the electrical power supply from the transformer station to the processing plant area. The construction of the first leaching pool and associated processing plant commenced in early 2017 and is now complete. The first trial batch of leaching commenced in June 2017